The Kings Beach Commercial Core Improvement Project utility relocation work along Highway 28 through Kings Beach is scheduled to resume this week and continue throughout the spring.

Listed below are dates and corresponding locations slated for this work:

March 19-22: Expect work to be conducted by the Log Cabin Caffe, eastbound Highway 28.

March 22-27: Expect work to be conducted by The Front Porch at the intersection of Fox Street and Highway 28, westbound Highway 28.

April 1-3: Expect work to be conducted by the Tahoe Forest Hospice Thrift Store at the intersection of Coon Street at Highway 28, westbound Highway 28.

April 8-12: Expect work between Coon and Bear streets.

Additional work areas will be added.

A minimum of one traffic lane will be open in each direction at all times while the utility relocation work takes place.

In addition to the Kings Beach CCIP utility relocation work, Southwest Gas will also be performing relocations in the vicinity. Most of the work conducted by Southwest Gas will be in the Kings Beach neighborhood “grid” area.

Click on the link below to view the utility exhibit which shows where relocations will be taking place.

 