By Kathryn Reed

South Tahoe Public Utility District board members on Wednesday somewhat hamstrung future board’s when it comes to allowable rate increases.

They also agreed to potential water and sewer increases that are well below what staff recommends.

“It really decreases the water line replacements. Hopefully, there is not a fire in the area where the water lines are pushed off,” Paul Hughes, CFO for the district, told Lake Tahoe News after the three-hour meeting.

Four of the board members clearly had their minds made up about how to proceed even before staff gave its report, and the public had a chance to ask questions and make comments.

Board member Chris Cefalu, who is out of town, didn’t even listen in during the March 26 discussion. He only joined the conversation via telephone when it came time for board deliberations.

He and board member Randy Vogelgesang were adamant that the staff’s recommendations were too much. Board members Eric Schafer and Jim Jones believe staff is spot on, with Jones saying increases could even be higher to meet the needs of the district. Kelly Sheehan didn’t say much, but leaned toward Cefalu and Vogelgesang.

In the end, the consensus was to set a maximum possible rate increase on the water side of 6.5 percent for each of the next four years with the fifth year being 5 percent; maximum possible sewer increase of 6 percent each of the next five years; and raising the base pay for those on water meters to be 80 percent of the bill, with 15 percent being based on consumption.

Staff had proposed water increases of 9.5 percent, 9 percent, 9 percent, 9 percent and 5 percent for the next five years. The other increases are what staff recommended.

Per state law the district must send to ratepayers what is called a Proposition 218 form. This informs them of the proposed maximum allowed increases. This will go out the first week of April.

Proposition 218 requires a 45-day protest period. If 50 percent plus one ratepayers were to file a protest to the proposed rate increases, the district could not go forward no matter what the board wanted to do.

It won’t be until the board’s June 5 meeting that a decision is actually made on what the increases, if there are any, will be. They can be less than what is proposed – including no increase. (There will also be public meetings April 17 and May 15, both at 6pm.)

What some of the board members were hung up on is this was not a vote for a specific percentage, but instead it was about a maximum allowed for the next five years.

One reason to go for the five-year Proposition 218 notice is to save money because the process is an expense, as well as to lock in revenues to pay for the completion of installing nearly 8,000 water meters.

The district has until mid-June to apply for a $21.5 million zero percent interest loan from the state that would be paid back over 20 years. The state is mandating water districts install meters by 2025.

Cefalu and Vogelgesang believe having put a higher cap on the rate increase would have made it more likely this and future boards would vote for that amount and they believe it is too much to ask ratepayers.

Schafer and Jones wanted to give this and future boards flexibility – plus, the top percentage allows the district to accomplish goals the board has set forth with capital improvement projects.

Besides needing to install the meters, the district’s main concerns are the nearly 1,500 residences that don’t have water lines that provide for adequate fire suppression. While the 2007 Angora Fire was brought up multiple times and how that area had sufficient sized lines, nothing was mentioned about California’s continued drought and how that could subject the area to greater danger of a wildfire. The 4-inch lines cannot pump the required 1,500 gallons per minute.

For the last 10 years, the average STPUD water bill has gone up 2 percent, and the sewer bill 2.55 percent.

When the district does its 10-year plan, which it updates every year, a 4 percent increase is forecast. This gives staff an idea of revenues so it can plan projects.

Schafer, who is the board president and has said he is not running for re-election in November, said of the 10-year document, “I think we need to start paying attention to what we put in it. That’s a semi-commitment.”

Because what has been going in it has not truly reflected the board’s actions because rate increases have not been occurring on a regular basis.

Staff showed how water projects for the next 10 years have a price tag of $69.5 million, while the 20-year estimate is $154 million. Ultimately the cost will be more expensive as things break and need to be repaired, and as construction costs escalate because costs are also based on work that should have been done.

And it’s possible after this five-year stretch rates could go higher to compensate for not having a higher rate now. That is essentially what is happening now. Staff had said 4 percent increases were needed to keep up with capital improvement projects. Those increases didn’t materialize because of board decisions. That is why larger increases were on the table.

The third issue facing the district is $58.5 million in capital improvements are penciled out for the next 10 years on the sewer side; $130 million across 20 years.

A fire that cannot be suppressed or a sewer spill into Lake Tahoe or the Upper Truckee River will prove making upgrades per staff recommendations should have done; plugging along without incident will prove the gamble with lower rate increases was the prudent move.

image_pdfimage_print

About author

This article was written by admin

Comments

Comments (7)
  1. dumbfounded says - Posted: March 26, 2014

    Has STPUD attempted to get excluded from the meter requirement? The meter technology will be difficult in this soil with normal weather conditions and the costs will be higher than anywhere else in the State. This should qualify Lake Tahoe for an exemption alone. If not that, then digging in the watershed should also qualify Lake Tahoe for an exemption. The TRPA should be involved. There is no reason to disturb that much soil and cause that much erosion to add unnecessary metering. How about it, STPUD?

  2. louis says - Posted: March 26, 2014

    dumb~ From what I remember when the law was passed for meters, STPUD sent lobbyists to put in a carve out for us because we aren’t a part of the rest of the California watershed. The politicians in Sac said no, because if we give a carve out for Tahoe, many other communities with lobbyists will ask for a carve out for whatever nonsense reason they make up.

    So blame who you will on this one, STPUD’s ineffective lobbyists, the powers that be in Sac. Take your choice. (oh and no you can’t entirely blame the democrats, because while they were in power is was Arnold a republican who signed off)

  3. Joby says - Posted: March 27, 2014

    Absolutely unbelievable! We already have an unfair disadvantage to those of us that had to pay to put in a meter. Put everyone on flat rate until meters are installed at all residences, or freeze the rates for those of us that are metered. I pay my fair share plus that of all the neighbors in my neighborhood. Infrastructure needs to be upgraded, I agree. Maybe the employees can forego raises for the next few years to help the cause. It is stated over and over “we haven’t raised rates in 3 years”, well neither have many of the business in town that compete in the real world. We funded your Taj Mahal administrative building, maybe some of that money should have gone towards the infrastructure. By the way my brother Chris is in Mexico helping the less fortunate building houses for Habitat to Humanity. So his missing the meeting was for a great cause.

  4. xlocal says - Posted: March 27, 2014

    Someone should check the wages of these people, they are over the top of any other business in the City by a large amount. Wow

  5. dumbfounded says - Posted: March 27, 2014

    Louis, I don’t believe that I attempted in any way to “blame the democrats”… I can’t imagine where that came from. I didn’t suggest any blame at all. We hear constantly that we cannot disturb the soil from the TRPA but now there are plans to disturb soil for 8,000 homes? Digging up all the shutoff valves alone will contribute to significant erosion. I would like to see that stopped.

  6. Marc says - Posted: March 27, 2014

    Does anyone know when fire suppression and adequate fire flow of 1500 gpm is mentioned is stpud referring to wildland urban interface fires, structure fires, wildland fires or all of the above?

  7. cosa pescado says - Posted: March 27, 2014

    ” Digging up all the shutoff valves alone will contribute to significant erosion. I would like to see that stopped”

    No it won’t.
    You really put the dumb in dumbfounded.